# Longview Bridge And Road, LTD.: TxDOT interchange (new or reconstructed) contract 93% complete, US 59, Nacogdoches County ($96,006,575, 21 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | American Remediation Options, INC. (1.36%); Mcl Contracting, LLC (4.22%); Dywidag-Systems International_usa,INC. (0.19%); Farr Foundation, INC. (0.28%); (Inactive)total Highway Maintenance, LLC (0.17%); John Wright Construction (3.01%); (Inactive)highway Intelligent Traffic Solutions, INC. (1.62%); Striping Technology, L.P. (0.3%); M & D Foundation Drilling Industries, INC. (2.11%); Bowman Engineering & Consulting, INC. (0.14%); Toro Bravo Construction, LLC (0.05%); (Inactive)aaron Concrete Contractors, L.P. (0.72%); J & Kd, L.L.C. (0.07%); Antigo Construction, INC. (0.05%); Snowhill Contracting LLC (0.32%); A&J Rebar LLC (3.1%); Matrix Concrete Road & Bridge, LLC (0.61%); Primate Construction, LP (0%); Kiteco Property Solutions INC. (0.07%); Drewery Construction Company, Incorporated (0.06%); Southeast Grinding And Grooving LLC (0%) |
| Progress | 92.58% complete, 99% of time used |
| Amount | $96,006,575 revised (original $86,198,369) |
| Change orders | $9,403,406 |
| Paid to date | $88,511,897 |
| Work | Interchange (New Or Reconstructed) |
| Location | US 59, SH 7 to 1.242 MI SOUTH OF SPRADLEY ST., Nacogdoches County, Lufkin District |
| Let / began | 2019-07-09 / 2019-08-20 |
| Latest estimate | 2026-10-05 |
| Contract number | 7193002 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.