# Longview Bridge And Road, LTD.: TxDOT widen non-freeway contract 59% complete, FM 2275, Gregg County ($23,669,860, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Longview Bridge And Road, LTD. |
| Subcontractors | Flex Supply, LLC (0.1%); Farr Foundation, INC. (1.41%); Hodges And Son Construction Company, INC. (1.44%); Kiteco Property Solutions INC. (0.29%); Toro Bravo Construction, LLC (1.17%); Withers Construction, LLC (1.14%); Morris County Contractors, L.L.C. (0.13%); Striping Technology, L.P. (0.61%); Southwest Environment Services LLC (0.16%); Cap River LLC (1.21%); Hx Farms, INC. (0.01%) |
| Progress | 58.81% complete, 48.41% of time used |
| Amount | $23,669,860 revised (original $22,863,768) |
| Change orders | $640,091 |
| Paid to date | $13,822,271 |
| Work | Widen Non-Freeway |
| Location | FM 2275, FM 3272 IN WHITE OAK, E to FM 1845 (PINE TREE RD) IN LONGVIEW, Gregg County, Tyler District |
| Let / began | 2025-08-07 / 2025-09-22 |
| Latest estimate | 2026-10-02 |
| Contract number | 8253002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.