# Lucania Contractors LLC: TxDOT bridge replacement contract 31% complete, CR, Cameron County ($1,406,641, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Lucania Contractors LLC |
| Subcontractors | Skyline Bridge LLC (9.59%); Texas Highway Systems, INC. (0.75%) |
| Progress | 30.5% complete, 51.72% of time used |
| Amount | $1,406,641 revised (original $1,389,617) |
| Paid to date | $423,826 |
| Work | Bridge Replacement |
| Location | CR, ON BROWNE AVE, 0.35 MI N OF SH 4 to STR# 210310AA0284001 @ DRAINAGE DIT, Cameron County, Pharr District |
| Let / began | 2026-03-04 / 2026-07-07 |
| Latest estimate | 2026-10-02 |
| Contract number | 3263029 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.