# Lucania Contractors LLC: TxDOT bridge replacement contract 88% complete, CS, Cameron County ($1,657,413, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Lucania Contractors LLC |
| Subcontractors | Highway Barricades And Services, LLC (0.53%); Beaird Drilling Services, INC. (10.45%); Texas Highway Systems, INC. (0.77%); Certified Placers LLC (0.15%); G&S Directional Drilling, LLC (1.22%); Skyline Bridge LLC (12.28%) |
| Progress | 88.19% complete, 145.59% of time used |
| Amount | $1,657,413 revised (original $1,646,413) |
| Paid to date | $1,451,889 |
| Work | Bridge Replacement |
| Location | CS, MINNESOTA AVE. @ DRAINAGE DITCH to NBI #: 210310C01256001, Cameron County, Pharr District |
| Let / began | 2025-08-07 / 2025-10-27 |
| Latest estimate | 2026-10-05 |
| Contract number | 8253017 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.