# Madden Contracting Company, LLC.: TxDOT widen non-freeway contract 98% complete, SH 204, Cherokee County ($17,760,412, 15 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Madden Contracting Company, LLC. |
| Subcontractors | A R Brothers Construction Services, INC. (1.99%); Cap River LLC (1.28%); Drewery Construction Company, Incorporated (4.31%); J. H. Oden Contracting Company (2.45%); Morris County Contractors, L.L.C. (1.83%); Panola Sign & Barricade, INC. (0.24%); R & G Construction, LLC (29.96%); Reynolds & Kay, LTD. (3.46%); Striping Technology, L.P. (1.62%); Southwest Environment Services LLC (0.49%); West Texas Rock Resources, LLC (0.08%); Forrest Hodges Operations, INC. (0.24%); Fredonia Services LLC (0.12%); Wms R And B, L.L.C. (0.58%); Aaba Mowing Contractors, Limited Liability Company (0.14%) |
| Progress | 97.81% complete, 133.96% of time used |
| Amount | $17,760,412 revised (original $16,863,171) |
| Change orders | $50,000 |
| Paid to date | $16,543,190 |
| Work | Widen Non-Freeway |
| Location | SH 204, SH 110, SE to RUSK C/L IN REKLAW, Cherokee County, Tyler District |
| Let / began | 2023-11-01 / 2024-02-09 |
| Latest estimate | 2026-10-02 |
| Contract number | 11233006 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.