# Madden Contracting Company, LLC.: TxDOT rehabilitation of existing road contract 100%+ complete, SS 63, Gregg County ($3,255,324, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Madden Contracting Company, LLC. |
| Subcontractors | Panola Sign & Barricade, INC. (0.84%); R & G Construction, LLC (0.82%); Striping Technology, L.P. (0%); Southwest Environment Services LLC (0.94%) |
| Progress | 107.6% complete, 51% of time used |
| Amount | $3,255,324 revised (original $3,172,923) |
| Paid to date | $3,414,160 |
| Work | Rehabilitation Of Existing Road |
| Location | SS 63, US 80 to SL 281, Gregg County, Tyler District |
| Let / began | 2026-02-04 / 2026-04-29 |
| Latest estimate | 2026-10-02 |
| Contract number | 2263015 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.