# Madden Contracting Company, LLC.: TxDOT rehabilitation of existing road contract 100%+ complete, SH 300, Upshur County ($24,813,485, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Madden Contracting Company, LLC. |
| Subcontractors | Cold Creek Construction, LTD (1.18%); J. H. Oden Contracting Company (0.66%); Morris County Contractors, L.L.C. (0.2%); Panola Sign & Barricade, INC. (0.79%); Reynolds & Kay, LTD. (5.85%); R & G Construction, LLC (15.06%); Southwest Environment Services LLC (0.14%); Striping Technology, L.P. (3.66%); Surface Preparation Technologies, LLC (0.06%) |
| Progress | 107.16% complete, 115.91% of time used |
| Amount | $24,813,485 revised (original $22,871,598) |
| Change orders | $1,196,886 |
| Paid to date | $25,791,686 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 300, 0.3 MI S OF US 271 to 0.1 MI N OF S FM 3358, Upshur County, Atlanta District |
| Let / began | 2024-04-04 / 2024-07-25 |
| Latest estimate | 2026-10-02 |
| Contract number | 4243003 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.