# Madden Contracting Company, LLC.: TxDOT rehabilitation of existing road contract 100%+ complete, SH 315, Rusk County ($21,451,375, 10 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Madden Contracting Company, LLC. |
| Subcontractors | West Texas Rock Resources, LLC (0.08%); Southwest Environment Services LLC (0.3%); Reynolds & Kay, LTD. (3.49%); Striping Technology, L.P. (1.36%); Panola Sign & Barricade, INC. (0.19%); Cap River LLC (0.32%); R & G Construction, LLC (5.36%); Morris County Contractors, L.L.C. (1.24%); Cold Creek Construction, LTD (1.64%); Isaacs Construction Services LLC (0.47%) |
| Progress | 102.76% complete, 114.94% of time used |
| Amount | $21,451,375 revised (original $13,565,152) |
| Change orders | $7,785,269 |
| Paid to date | $21,939,495 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 315, US 259 to PANOLA CL, Rusk County, Tyler District |
| Let / began | 2023-06-01 / 2024-01-11 |
| Latest estimate | 2026-10-02 |
| Contract number | 6233005 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.