# Mario Sinacola & Sons Excavating, INC.: TxDOT widen freeway contract 100%+ complete, US 75, Collin County ($81,103,679, 23 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Mario Sinacola & Sons Excavating, INC. |
| Subcontractors | Traffic Highway Maintenance, LLC (0.59%); Oscar Orduno, INC. (1.02%); Scott Derr Painting Co, LLC (0.05%); Texas Environmental Management - San Antonio, INC. (2.21%); Imt Construction, LLC (0.58%); Antigo Construction, INC. (0.08%); Toro Bravo Construction, LLC (0.71%); Jose Lemus Trucking (0%); Cowboy Trucking (0.27%); Red Top Trucking LLC (0.82%); T-Bar Fence, INC. (0.01%); Wylie Drilling & Drainage, INC. (0.18%); Texas Select Erosion, LLC (0.29%); Rcf Construction, LLC (1.1%); Act Saw Cutting & Removal (0.2%); Texop Construction (0.69%); Stoic Civil Construction, INC. (0.86%); Tor Texas, LLC (0.14%); Fc Traffic Control, INC. (0.35%); Southern Cross Contractors, LLC (0.47%); Reynolds Asphalt & Construction Company (14.27%); Florida Traffic Control Devices, INC. (1.45%); Stripe-A-Zone, LLC (0.59%) |
| Progress | 101.14% complete, 96.42% of time used |
| Amount | $81,103,679 revised (original $80,040,840) |
| Change orders | $39,039 |
| Paid to date | $80,994,721 |
| Work | Widen Freeway |
| Location | US 75, NORTH OF CR 370 to CR 375 (GRAYSON COUNTY LINE), Collin County, Dallas District |
| Let / began | 2024-01-04 / 2024-04-29 |
| Latest estimate | 2026-10-05 |
| Contract number | 1243001 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.