# Massana Construction INC.: TxDOT hazard elimination & safety contract 78% complete, US 62, Lubbock County ($3,267,634, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Massana Construction INC. |
| Subcontractors | Jvh4 Services, LLC (0.25%); Fc Traffic Control, INC. (0.57%); Gorman Outdoor, INC. (0.94%); Desert West Enterprises LLC (0.57%); Lone Star Dirt & Paving, LTD. (12.05%) |
| Progress | 78.11% complete, 21.78% of time used |
| Amount | $3,267,634 revised (original $2,699,559) |
| Change orders | $528,125 |
| Paid to date | $2,521,013 |
| Work | Hazard Elimination & Safety |
| Location | US 62, HOCKLEY COUNTY LINE to 73RD ST IN LUBBOCK, Lubbock County, Lubbock District |
| Let / began | 2025-08-08 / 2026-01-05 |
| Latest estimate | 2026-10-06 |
| Contract number | 8253210 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.