# Missouri Petroleum Products Company: TxDOT seal coat contract 92% complete, SH 8, Bowie County ($12,836,501, 3 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Missouri Petroleum Products Company |
| Subcontractors | Barricades Plus, LLC (2.08%); Innovative Roadway Solutions, LLC (4.91%); Striping Technology, L.P. (8.87%) |
| Progress | 92.33% complete, 106.73% of time used |
| Amount | $12,836,501 revised (original $12,311,054) |
| Change orders | $491,447 |
| Paid to date | $11,820,795 |
| Work | Seal Coat |
| Location | SH 8, ARKANSAS S/L to 2.9 MI S OF ARKANSAS S/L, Bowie County, Atlanta District |
| Let / began | 2025-10-09 / 2026-04-06 |
| Latest estimate | 2026-10-05 |
| Contract number | 10253234 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.