# Mortmara Construction, INC.: TxDOT bridge replacement contract 77% complete, US 287, Hardeman County ($30,379,848, 20 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Mortmara Construction, INC. |
| Subcontractors | G & L Rebar (0.63%); Jb Pinnacle Group, LLC (7.09%); Mcryan Hauling, INC. (0.39%); Macias Specialty Contracting LLC (0.54%); Wolfe Construction Group, Incorporated (0.18%); Concrete Coring Company (0.32%); Texas Shafts, INC. (5.66%); Penhall Company (0.11%); King George Traffic Solutions LLC (0.62%); Blacksmith Ventures LLC (10.3%); Highpoint Partners, LLC (11.37%); Traffic Highway Maintenance, LLC (0.69%); Stripe-A-Zone, LLC (0.69%); Oscar Orduno, INC. (1.45%); Hjc Farms, INC. (1.48%); Davis Motor Crane Service, INC. (1.22%); Hermanos Steel, LLC (0%); Corsair Consulting LLC (0.16%); Trp Construction Group, LLC (0.63%); Zack Burkett Co. (0.72%) |
| Progress | 77.15% complete, 76.83% of time used |
| Amount | $30,379,848 revised (original $28,987,860) |
| Change orders | $1,391,988 |
| Paid to date | $23,437,893 |
| Work | Bridge Replacement |
| Location | US 287, @ BNSF RR & LP 285 to ., Hardeman County, Childress District |
| Let / began | 2024-06-06 / 2024-09-16 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243206 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.