# Mp Heavy Construction INC: TxDOT bridge replacement contract 42% complete, US 287, Houston County ($9,031,788, 16 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Mp Heavy Construction INC |
| Subcontractors | Texas Bridge And Paving, LLC (3.18%); Jb Pinnacle Group, LLC (0.38%); Cap River LLC (2.29%); Diibs Specialists, LLC (0.37%); J & M Contracting, Company (1.13%); Toro Bravo Construction, LLC (0.37%); Texas Materials Group, INC. (12.54%); Pinto Construction Co., INC. (11.07%); Interstate Barricades & Markings, INC. (0.8%); Hermanos Steel, LLC (1.89%); Beavers Milling Services LLC (0.38%); Texas Shafts, INC. (1.95%); Onnea Equipment LLC (2.75%); 4e Tree Worx LLC (0.84%); Fc Traffic Control, INC. (0.2%); Bobcat Crane, LLC (1.05%) |
| Progress | 41.76% complete, 99.09% of time used |
| Amount | $9,031,788 revised (original $8,999,168) |
| Change orders | $29,620 |
| Paid to date | $3,769,993 |
| Work | Bridge Replacement |
| Location | US 287, AT BEAVER CREEK to ., Houston County, Lufkin District |
| Let / began | 2024-08-02 / 2025-01-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 8243215 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.