# Nobles Road Construction, INC.: TxDOT widen non-freeway contract 23% complete, FM 608, Nolan County ($8,057,062, 3 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Nobles Road Construction, INC. |
| Subcontractors | Hjc Farms, INC. (1.79%); Dk Contracting, LLC (0.9%); Ag2 Construction Corp (7.03%) |
| Progress | 23.06% complete, 92.58% of time used |
| Amount | $8,057,062 revised (original $7,895,450) |
| Change orders | $157,612 |
| Paid to date | $1,857,143 |
| Work | Widen Non-Freeway |
| Location | FM 608, .010MI EAST OF SECOND ST IN MARYNEA to SH 70, Nolan County, Abilene District |
| Let / began | 2024-11-06 / 2025-04-14 |
| Latest estimate | 2026-10-06 |
| Contract number | 11243014 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.