# Northeastern Pavers, LLC: TxDOT maintenance contract 58% complete, IH0020, Palo Pinto County ($7,141,551)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Northeastern Pavers, LLC |
| Progress | 57.92% complete, 43.7% of time used |
| Amount | $7,141,551 revised (original $6,554,076) |
| Change orders | $589,000 |
| Paid to date | $4,136,919 |
| Work | Maintenance |
| Location | IH0020, VARIOUS LOCATIONS WITHIN to PALO PINTO COUNTY, Palo Pinto County, Fort Worth District |
| Let / began | 2025-08-08 / 2025-11-11 |
| Latest estimate | 2026-09-28 |
| Contract number | 8254204 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.