# O. Trevino Construction, LLC: TxDOT overlay contract 62% complete, SS 557, Kaufman County ($8,667,868, 8 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | O. Trevino Construction, LLC |
| Subcontractors | Hjc Farms, INC. (8.64%); Texas Materials Group, INC. (38.25%); Professional Traffic Control LLC (0.16%); Brenda Price Trucking, INC. (1.63%); USA Swppp Inspections, INC. (0.24%); (Inactive)site Barricades (0.2%); The Confidence Group, INC (1.1%); Dustrol, INC. (1.03%) |
| Progress | 61.6% complete, 76.54% of time used |
| Amount | $8,667,868 revised (original $8,281,477) |
| Change orders | $356,291 |
| Paid to date | $5,320,816 |
| Work | Overlay |
| Location | SS 557, US 80 to IH 20, Kaufman County, Dallas District |
| Let / began | 2025-11-05 / 2026-02-23 |
| Latest estimate | 2026-10-02 |
| Contract number | 11253008 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.