# Orion Construction, LLC: TxDOT bridge replacement contract 46% complete, SH 6, Mclennan County ($113,488,271, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Orion Construction, LLC |
| Subcontractors | A. H. Beck Foundation Co., INC. (18.21%); Texas Steel Industrial Placing, LLC (0%); Trp Construction Group, LLC (0.3%); Environmental Safety Services, INC. (0.78%); A Brothers Milling, LLC (0.03%); Cowboy Trucking (0.48%); Jb Pinnacle Group, LLC (1.02%); Primate Construction, LP (0.11%); Lone Star Paving Company (1.34%); F & W Electrical Contractors, INC. (0.23%); Texas Clear Cut LLC (0.41%); Apple Personnel Service, INC. (0%); Terracon Consultants, INC. (0.44%); Texas Steel Industrial Placing, Concrete Division LLC (0%); Darkhorse Industries, L.L.C. (0.37%) |
| Progress | 46.25% complete, 31.24% of time used |
| Amount | $113,488,271 revised (original $113,740,588) |
| Change orders | $-1,397,317 |
| Paid to date | $51,959,640 |
| Work | Bridge Replacement |
| Location | SH 6, AT LAKE WACO to ., Mclennan County, Waco District |
| Let / began | 2025-01-08 / 2025-03-31 |
| Latest estimate | 2026-10-01 |
| Contract number | 1253203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.