# Orion Construction, LLC: TxDOT bridge replacement contract 100%+ complete, SH 317, Bosque County ($6,695,166, 14 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Orion Construction, LLC |
| Subcontractors | Diibs Specialists, LLC (0.86%); T-Bar Fence, INC. (1.74%); Traffic Highway Maintenance, LLC (0.72%); Texas Steel Industrial Placing, LLC (0.54%); Scott Derr Painting Co, LLC (0.06%); Texas Clear Cut LLC (9.57%); Gk Construction, LLC (0%); Lone Star Paving Company (4.87%); Rucoba & Maya Construction, LLC (4.74%); Jb Pinnacle Group, LLC (1.23%); 1 Priority Environmental Services, LLC (0.17%); Darkhorse Industries, L.L.C. (0.25%); Beaird Drilling Services, INC. (2.68%); Wolfe Construction Group, Incorporated (0.31%) |
| Progress | 103.27% complete, 100% of time used |
| Amount | $6,695,166 revised (original $6,597,547) |
| Change orders | $97,618 |
| Paid to date | $6,914,122 |
| Work | Bridge Replacement |
| Location | SH 317, BNSF RAILROAD to FROM STA. 108+20.00 TO STA. 126+68.00, Bosque County, Waco District |
| Let / began | 2025-03-05 / 2025-09-22 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253211 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.