# Overland Corporation: TxDOT overlay contract 100%+ complete, US 82, Grayson County ($11,306,571, 5 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Overland Corporation |
| Subcontractors | Linear Traffic Markings LLC (2.38%); J. H. Oden Contracting Company (1.05%); Superior Traffic Control, LLC (0.52%); Texop Construction (2.01%); West Texas Rock Resources, LLC (0.5%) |
| Progress | 128.36% complete, 253.19% of time used |
| Amount | $11,306,571 revised (original $10,591,400) |
| Paid to date | $13,594,784 |
| Work | Overlay |
| Location | US 82, US 82 FROM 1.3 MI W OF FM 1417 TO GRAYSON/FANNIN CTY LINE, Grayson County, Paris District |
| Let / began | 2024-06-06 / 2025-04-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243219 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.
