# Pathfield Investments LLC: TxDOT bridge widening or rehabilitation contract 41% complete, SH 214, Parmer County ($4,299,134, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Pathfield Investments LLC |
| Subcontractors | Trp Construction Group, LLC (1.39%); Tex Op Construction, LP (0.51%); Fc Traffic Control, INC. (0.22%) |
| Progress | 41.2% complete, 75.64% of time used |
| Amount | $4,299,134 revised (original $4,197,908) |
| Paid to date | $1,729,453 |
| Work | Bridge Widening Or Rehabilitation |
| Location | SH 214, 0.05 MILES SOUTH OF BNSF RR to ON SH 214, Parmer County, Lubbock District |
| Let / began | 2025-09-04 / 2026-03-23 |
| Latest estimate | 2026-10-06 |
| Contract number | 9253021 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.