# Pinto Construction Co., INC.: TxDOT rehabilitation of existing road contract 95% complete, US 96, Sabine County ($15,437,575, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Pinto Construction Co., INC. |
| Subcontractors | Dustrol, INC. (0.26%); A. L. Helmcamp, INC. (0.36%); A R Brothers Construction Services, INC. (5.6%); American Remediation Options, INC. (1.2%); Cap River LLC (0.71%); Cold Creek Construction, LTD (1.29%); Interstate Barricades & Markings, INC. (0.64%); Panola Sign & Barricade, INC. (0.33%); Texas Materials Group, INC. (50.82%); Third Coast Services LLC (1.76%); West Texas Rumble Strip LLC (0.06%) |
| Progress | 94.68% complete, 59.13% of time used |
| Amount | $15,437,575 revised (original $14,650,398) |
| Change orders | $684,929 |
| Paid to date | $14,519,987 |
| Work | Rehabilitation Of Existing Road |
| Location | US 96, FM 83 to 0.50 MILES SOUTH OF SPUR 414, Sabine County, Lufkin District |
| Let / began | 2025-07-01 / 2025-09-16 |
| Latest estimate | 2026-10-05 |
| Contract number | 7253002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.