# Pmco Construction LLC: TxDOT bridge replacement contract 64% complete, FM 1580, Freestone County ($2,622,032, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Pmco Construction LLC |
| Subcontractors | M & D Foundation Drilling Industries, INC. (4.47%); Highway Traffic Control & Services, LLC (0.93%); J. H. Oden Contracting Company (2.19%); Texas Materials Group, INC. (5.08%); Texop Construction (0.87%); Morris County Contractors, L.L.C. (2.92%); Striping Technology, L.P. (0.92%) |
| Progress | 64.28% complete, 73.68% of time used |
| Amount | $2,622,032 revised (original $2,573,940) |
| Paid to date | $1,654,489 |
| Work | Bridge Replacement |
| Location | FM 1580, AT MIMS CREEK to ., Freestone County, Bryan District |
| Let / began | 2025-10-08 / 2026-02-16 |
| Latest estimate | 2026-09-30 |
| Contract number | 10253024 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.