# Pmco Construction LLC: TxDOT bridge replacement contract 50% complete, BI 45F, Navarro County ($3,946,000, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Pmco Construction LLC |
| Subcontractors | Highway Traffic Control & Services, LLC (1.93%); Striping Technology, L.P. (2.86%); Wolfe Construction Group, Incorporated (0.49%); Big Creek Construction, LTD. (17.39%); M & D Foundation Drilling Industries, INC. (3.17%); Fortson Contracting, INC. (3.29%); S&S Bridge Painting (0.24%) |
| Progress | 49.56% complete, 92.5% of time used |
| Amount | $3,946,000 revised (original $3,850,000) |
| Paid to date | $1,907,934 |
| Work | Bridge Replacement |
| Location | BI 45F, AT POST OAK CREEK to ., Navarro County, Dallas District |
| Let / began | 2025-05-01 / 2026-01-05 |
| Latest estimate | 2026-10-02 |
| Contract number | 5253013 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.