# Posillico Civil, INC.: TxDOT upgrade to standards freeway contract 37% complete, US 77, Kenedy County ($195,368,473, 18 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Posillico Civil, INC. |
| Subcontractors | D&G Energy Corporation (0.98%); Izaguirre Construction LLC (0.29%); Pave/Lock/Plus II, LLC (0.11%); Texas Environmental Management - San Antonio, INC. (1.55%); Certified Placers LLC (0.06%); Memco Staffing, LLC (0%); Houston Sawing & Drilling (0.02%); Texas Elite Hauling Services, INC. (0.18%); Siboney Contracting Co. (0.32%); Texas Cordia Construction, LLC (0.06%); K. L. Durham Construction, L.L.C. (0.77%); Frontier Development, INC. (0.08%); Highway Barricades And Services, LLC (0.65%); J.H. Painting Company (0.14%); Gregory Pile Driving, INC. (0.37%); D&L Transport, LLC (0.16%); G & E Escobedo Construction, INC. (0%); G.E.O. Construction, LLC (0.15%) |
| Progress | 36.87% complete, 54.25% of time used |
| Amount | $195,368,473 revised (original $190,998,296) |
| Change orders | $543,677 |
| Paid to date | $70,612,736 |
| Work | Upgrade To Standards Freeway |
| Location | US 77, NORIAS RD to 1.34 MI N OF WILLACY/KENEDY C.L., Kenedy County, Pharr District |
| Let / began | 2023-12-05 / 2024-07-11 |
| Latest estimate | 2026-09-30 |
| Contract number | 12233028 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.