# Posillico Civil, INC.: TxDOT restoration contract 81% complete, SH 275, Galveston County ($8,809,253, 11 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Posillico Civil, INC. |
| Subcontractors | Texas Bro's Sawing And Sealing LLC (2.06%); Scott Derr Painting Co, LLC (1.79%); Curb Planet INC. (0.05%); Doran Steel, INC. (1.08%); Sitek Omni Services, LLC (2.74%); East Texas R & D Services, INC. (1.34%); Cherry Moving Company, INC. (0.42%); Railpros Field Services, INC. (0.58%); Traffic Signs & Lines, LLC (9.62%); A-Core Concrete Cutting Of Texas, INC. (7.04%); Performance Equipment Service (1.42%) |
| Progress | 81.2% complete, 93.89% of time used |
| Amount | $8,809,253 revised (original $9,764,259) |
| Change orders | $-1,310,007 |
| Paid to date | $6,865,268 |
| Work | Restoration |
| Location | SH 275, 77TH STREET to 51ST STREET, Galveston County, Houston District |
| Let / began | 2025-06-04 / 2025-11-17 |
| Latest estimate | 2026-09-30 |
| Contract number | 6253012 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.