# Posillico Civil, INC.: TxDOT newlocation non-freeway contract 49% complete, SL 195, Starr County ($62,522,900, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Posillico Civil, INC. |
| Subcontractors | Certified Placers LLC (0.4%); Strata Foundation Drilling, LLC (0.67%); Texas Environmental Management - San Antonio, INC. (1.06%); Tnt Crane & Rigging, INC. (0.02%); Emery Sapp Construction, INC. (0.19%); D&G Energy Corporation (0.88%); Highway Barricades And Services, LLC (0.29%); Hurricane Fence Company (0.46%); Murray Construction (0.22%); Drill Tech Drilling & Shoring, INC. (1.36%) |
| Progress | 49.22% complete, 27.95% of time used |
| Amount | $62,522,900 revised (original $62,281,400) |
| Paid to date | $30,655,445 |
| Work | Newlocation Non-Freeway |
| Location | SL 195, NEW LOCATION, FM 3167 to FM 755, Starr County, Pharr District |
| Let / began | 2025-09-05 / 2026-01-12 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.