# Prater Dirt Work LLC: TxDOT rehabilitation of existing road contract 90% complete, IH 20, Parker County ($5,139,627, 8 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Prater Dirt Work LLC |
| Subcontractors | Zack Burkett Co. (18.44%); Dustrol, INC. (0.57%); Jr West Texas Concrete LLC (22.86%); Synergy Signs & Services LLC (5.06%); Hilbash Investment LLC (5.03%); Texas Environmental Management - San Antonio, INC. (1.64%); Traffic Highway Maintenance, LLC (1.77%); Ibctx, LLC (2.5%) |
| Progress | 90.19% complete, 129.61% of time used |
| Amount | $5,139,627 revised (original $5,099,675) |
| Change orders | $39,944 |
| Paid to date | $4,635,400 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 20, AT WESTBOUND EXIT to RANCH HOUSE ROAD, Parker County, Fort Worth District |
| Let / began | 2025-07-02 / 2025-11-06 |
| Latest estimate | 2026-10-06 |
| Contract number | 7253242 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.