# Pulice Construction, INC.: TxDOT widen freeway contract 54% complete, IH 10, Colorado County ($413,896,405, 33 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Pulice Construction, INC. |
| Subcontractors | Long Legacy Enterprises, LLC (0.03%); Buyers Barricades San Antonio, LLC (0.01%); Massana Construction INC. (0.2%); Doran Steel, INC. (0%); A&J Rebar LLC (0%); American Signal Equipment Co., INC. (Converse) (0%); Allstate Signal & Construction, LLC (4.06%); Quality Turf Farms, L.C. (0.3%); Trp Construction Group, LLC (0.48%); Williams Road, LLC (0.31%); Badeco, INC. (0.04%); A. H. Beck Foundation Co., INC. (4.11%); Shuffield Land Clearing & Services, LLC (0%); Sarens USA, INC. (0.02%); Primate Construction, LP (0.24%); Willow City Sign & Rail, INC. (0.4%); Texas Lawn Care Group, LLC (0%); Sweeping Corporation Of America, LLC (0.19%); Mammoet USA South, INC. (0.08%); Texas Clear Cut LLC (5.24%); Choctaw Erectors, INC. (0.82%); Antigo Construction, INC. (0.12%); Gmj Paving Company LLC (7.19%); A R Daniel Construction Services, Incorporated (0.04%); Tnt Crane & Rigging, INC. (0.03%); Batten Drilling, INC. (0%); Texas Steel Industrial Placing, LLC (0.27%); Penhall Company (0%); Durwood Greene Construction Co. (7.19%); Epcs Demolition LLC (0.73%); Epcs Environmental LLC (0%); Jbc Consolidated, LLC (0.4%); Roadway Specialties, INC. (0.56%) |
| Progress | 54.08% complete, 44.35% of time used |
| Amount | $413,896,405 revised (original $404,972,361) |
| Change orders | $4,053,231 |
| Paid to date | $221,220,214 |
| Work | Widen Freeway |
| Location | IH 10, COLORADO RIVER BRIDGE to US 90 (ALLEYTON RD SOUTH), Colorado County, Yoakum District |
| Let / began | 2024-05-03 / 2024-10-14 |
| Latest estimate | 2026-10-05 |
| Contract number | 5243201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.