# Pulice Construction, INC.: TxDOT widen non-freeway contract 100% complete, SH 36, Brazoria County ($136,186,494, 35 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Pulice Construction, INC. |
| Subcontractors | Antigo Construction, INC. (0.12%); Gmj Paving Co. (4.29%); Quality Turf Farms, L.C. (1.3%); A&J Rebar LLC (0.02%); Buyers Barricades Houston, LLC (0.01%); Joslin Construction Texas, LLC (0.97%); Allstate Signal & Construction, LLC (3.91%); A Brothers Milling, LLC (0.83%); Pmi Pavement Marking, LLC (0.43%); Double Oak Erosion, INC. (0.17%); Weber-Balke Foundation Company, INC (0.26%); Kay Savage Trucking, INC. (0.35%); Buyers Barricades, INC. (0.01%); (Inactive)stripe-A-Zone, INC. (0.01%); Willow City Sign & Rail, INC. (1.09%); Highway Pavement Specialties, INC. (0.2%); Tandem Lamarr Trucking & Excavating, INC. (1.36%); Mcneil Brothers, INC. (6.09%); Bella Paving, INC. (0.09%); Hi-Tech Concree Pumping Services (0%); Batterson, LLP (0.4%); A-Core Concrete Cutting Of Texas, INC. (0.01%); Sk Concrete Services LLC (0.14%); Bortunco (0.05%); Mcnorton Dewatering, INC. (0.01%); Dj21 Transport INC (0.77%); Cgc Logistics (0.04%); Lift Ckc, LLC (0.19%); F & L Coatings And Concrete, L.L.C. (0.01%); Ace Controls Acquisition Company, LLC (0.01%); Cv Electrical Services Of Texas (0.02%); Penhall Company (0%); Surface Preparation Technologies, LLC (0.06%); Chiron Communication Services, LLC (0.34%); Durwood Greene Construction Co. (4.29%) |
| Progress | 99.58% complete, 100% of time used |
| Amount | $136,186,494 revised (original $75,955,686) |
| Change orders | $60,048,808 |
| Paid to date | $135,438,590 |
| Work | Widen Non-Freeway |
| Location | SH 36, FORT BEND COUNTY LINE to N OF CR 467/HOGG RANCH RD, Brazoria County, Houston District |
| Let / began | 2019-09-05 / 2020-02-03 |
| Latest estimate | 2026-09-30 |
| Contract number | 9193004 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.