# Pulice Construction, INC.: TxDOT widen non-freeway contract 100%+ complete, SH 36, Fort Bend County ($58,875,939, 25 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Pulice Construction, INC. |
| Subcontractors | Pmi Pavement Marking, LLC (0.62%); Buyers Barricades Houston, LLC (0.03%); Antigo Construction, INC. (0.15%); Quality Turf Farms, L.C. (1.51%); Gmj Paving Co. (5.82%); A&J Rebar LLC (0.64%); Buyers Barricades, INC. (0.03%); Willow City Sign & Rail, INC. (0.79%); Kay Savage Trucking, INC. (1.29%); A Brothers Milling, LLC (0.94%); Weber-Balke Foundation Company, INC (1.38%); Double Oak Erosion, INC. (0.4%); Allstate Signal & Construction, LLC (5.48%); Highway Pavement Specialties, INC. (0.22%); Tandem Lamarr Trucking & Excavating, INC. (1.47%); Yellowstone Landscape - Central, INC. (0.01%); Doran Steel, INC. (0.04%); Bella Paving, INC. (0.1%); Mcneil Brothers, INC. (6.84%); Hi-Tech Concree Pumping Services (0.03%); Batterson, LLP (0.56%); A-Core Concrete Cutting Of Texas, INC. (0.03%); Sk Concrete Services LLC (0.06%); Chiron Communication Services, LLC (0.19%); Surface Preparation Technologies, LLC (0.1%) |
| Progress | 100.95% complete, 96.41% of time used |
| Amount | $58,875,939 revised (original $42,315,989) |
| Change orders | $16,163,529 |
| Paid to date | $59,034,909 |
| Work | Widen Non-Freeway |
| Location | SH 36, 0.284 MI S OF NEEDVILLE-FAIRCHILD to BRAZORIA C/L, Fort Bend County, Houston District |
| Let / began | 2019-09-06 / 2020-01-08 |
| Latest estimate | 2026-09-30 |
| Contract number | 9193205 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.