# Pulice Construction, INC.: TxDOT widen non-freeway contract 70% complete, US 69, Tyler County ($223,595,182, 31 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Pulice Construction, INC. |
| Subcontractors | Eas-Tex Contractors, INC. (0%); Eastex Utility Construction, LLC (1.54%); George Meeks Landpro, INC. (0%); Valley Placers, LLC (0.12%); Texas Sterling Construction Co. (1.4%); Eagle Construction LLC (5.39%); Quality Turf Farms, L.C. (0.68%); Epcs Environmental LLC (0%); Weber-Balke Foundation Company, INC (0.89%); Texas Steel Industrial Placing, LLC (0.58%); Texas Steel Industrial Placing, Concrete Division LLC (0%); Tiger Creek Enterprises, INC. (0.02%); Batterson, LLP (0.61%); Gmj Paving Company LLC (2.89%); Prime Trees INC. (0.67%); Wampole Miller, INC. (0.69%); Clearview Clearing & Site Service, INC (0.2%); Mcneil Brothers, INC. (6.94%); Jb Pinnacle Group, LLC (0.15%); Sk Concrete Services LLC (0.18%); Jt Underground And Utility Construction INC (0.11%); G & T Traffic Solutions, LLC (0%); Long Legacy Enterprises, LLC (0.55%); Keller North America, INC. (0.13%); A&J Rebar LLC (0.46%); (Inactive)royal Rebar (0.69%); John Wright Construction (0.12%); Southwest Road & Safety Contractors, LTD. (1.44%); Antigo Construction, INC. (0.05%); Performance Equipment Service (0.27%); 4-Way Haulers, LLC (0.39%) |
| Progress | 70.19% complete, 83.69% of time used |
| Amount | $223,595,182 revised (original $205,416,130) |
| Change orders | $18,179,052 |
| Paid to date | $156,935,538 |
| Work | Widen Non-Freeway |
| Location | US 69, 0.1 MI SOUTH OF BLACK CREEK to HARDIN COUNTY LINE, Tyler County, Beaumont District |
| Let / began | 2023-09-06 / 2023-12-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 9233001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.