# Quality Excavation, LLC: TxDOT traffic signal contract 79% complete, FM 428, Denton County ($1,593,457, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Quality Excavation, LLC |
| Subcontractors | Overland Corporation (26.9%); Surface Preparation Technologies, LLC (0.15%); Urbanglow Contracting LLC (16.73%); Texas Environmental Management - San Antonio, INC. (3.39%); Southern Cross Contractors, LLC (1.09%); Dustrol, INC. (3.69%); Stripe-A-Zone, LLC (1.45%) |
| Progress | 79.16% complete, 83.16% of time used |
| Amount | $1,593,457 revised (original $1,537,357) |
| Paid to date | $1,216,915 |
| Work | Traffic Signal |
| Location | FM 428, WEST OF FM 2931 to EAST OF FM 2931, Denton County, Dallas District |
| Let / began | 2026-01-07 / 2026-06-01 |
| Latest estimate | 2026-10-02 |
| Contract number | 1263220 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.