# Ragle Construction, INC.: TxDOT bridge widening or rehabilitation contract 13% complete, IH 20, Dallas County ($8,218,623, 7 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Ragle Construction, INC. |
| Subcontractors | Elite Striping, LLC (0.15%); Hydro Technologies, INC. (14.37%); Tex Op Construction, LP (1.58%); Act Saw Cutting & Removal (0.23%); A-Core Concrete Cutting Of Texas, INC. (1.43%); Straight Line Sawing & Sealing, INC. (0.21%); H Torres Trucking, L.L.C. (0.03%) |
| Progress | 13.02% complete, 57.89% of time used |
| Amount | $8,218,623 revised (original $7,984,023) |
| Paid to date | $1,039,261 |
| Work | Bridge Widening Or Rehabilitation |
| Location | IH 20, BONNIE VIEW ROAD to IH 635, Dallas County, Dallas District |
| Let / began | 2026-02-04 / 2026-05-06 |
| Latest estimate | 2026-10-02 |
| Contract number | 2263007 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.