# Ragle Construction, INC.: TxDOT widen freeway contract 68% complete, SH 183, Tarrant County ($28,773,811, 19 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ragle Construction, INC. |
| Subcontractors | Double S Construction (0.09%); J. Ruedas Trucking, LLC (0%); Railpros Field Services, INC. (0.01%); Alpha Testing, INC. (0.55%); USA Swppp Inspections, INC. (0.07%); Traffic Tech Solutions, LLC (2.6%); Blue Bird Construction, LLC (0.18%); H Torres Trucking, L.L.C. (0.01%); J Munoz Trucking LLC (0%); Ancortex, INC. (17.34%); King George Traffic Solutions LLC (0.1%); Act Saw Cutting & Removal (0.06%); Choctaw Erectors, INC. (5.87%); Dustrol, INC. (0.08%); Hermanos Steel, LLC (5.18%); Linear Traffic Markings LLC (0.17%); Reynolds Asphalt & Construction Company (1.76%); Brenda Price Trucking, INC. (0%); Fortson Contracting, INC. (0.09%) |
| Progress | 68.38% complete, 106.34% of time used |
| Amount | $28,773,811 revised (original $26,588,577) |
| Change orders | $1,081,337 |
| Paid to date | $18,921,460 |
| Work | Widen Freeway |
| Location | SH 183, AT UPRR RAILROAD & UPRR SPUR to ., Tarrant County, Fort Worth District |
| Let / began | 2023-03-07 / 2023-10-31 |
| Latest estimate | 2026-10-05 |
| Contract number | 3233003 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.