# Ragle Construction, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, BI 20E, Ector County ($25,331,063, 15 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Ragle Construction, INC. |
| Subcontractors | Peyson Transport, LLC (1.74%); Willis Electric Co., LP (0.83%); Texas Environmental Management - San Antonio, INC. (0.77%); Southwest Road & Safety Contractors, LTD. (2.07%); Hjc Farms, INC. (0.05%); Fibertex, LLC (0.03%); 1 Priority Environmental Services, LLC (1.24%); Fc Traffic Control, INC. (0.14%); 4-Way Haulers, LLC (1.74%); Rubio's Paving (0.07%); Sk Concrete Services LLC (0.18%); Act Saw Cutting & Removal (0.16%); A Brothers Milling, LLC (1.35%); Diamond C Logistics Tx LLC (1.74%); Double A Contracting, L.P. (1.2%) |
| Progress | 112.84% complete, 96.15% of time used |
| Amount | $25,331,063 revised (original $23,137,298) |
| Change orders | $927,575 |
| Paid to date | $27,153,938 |
| Work | Rehabilitation Of Existing Road |
| Location | BI 20E, 8th to Country Club, Faudree to FM 1788 to 1m E of FM 1788, Ector County, Odessa District |
| Let / began | 2023-03-07 / 2023-10-16 |
| Latest estimate | 2026-10-01 |
| Contract number | 3233005 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.