# Ragle Construction, INC.: TxDOT bridge replacement contract 70% complete, IH 20, Howard County ($14,413,151, 12 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ragle Construction, INC. |
| Subcontractors | Morris County Contractors, L.L.C. (0.83%); Bay LTD. (0.15%); Bag Reinforcing LLC (0.97%); Willis Electric Co., LP (7.73%); Traffic Highway Maintenance, LLC (1.27%); Sk Concrete Services LLC (0.06%); S & S Bridge Painting, INC. (0.24%); Peyson Transport, LLC (0.51%); Southwest Road & Safety Contractors, LTD. (1.19%); Toro Bravo Construction, LLC (0.11%); M & D Foundation Drilling Industries, INC. (2.08%); 1 Priority Environmental Services, LLC (0.75%) |
| Progress | 70.3% complete, 58.44% of time used |
| Amount | $14,413,151 revised (original $14,287,270) |
| Change orders | $115,881 |
| Paid to date | $10,125,870 |
| Work | Bridge Replacement |
| Location | IH 20, SH 350 to I 20, Howard County, Abilene District |
| Let / began | 2025-03-04 / 2025-09-23 |
| Latest estimate | 2026-10-06 |
| Contract number | 3253005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.