# Red Baron Building Company, LLC: TxDOT maintenance contract 89% complete, US0080, Wood County ($177,044)

**Score:** 35/100

| Field | Value |
|---|---|
| Prime contractor | Red Baron Building Company, LLC |
| Progress | 89.16% complete, 85.51% of time used |
| Amount | $177,044 revised (original $143,287) |
| Change orders | $33,750 |
| Paid to date | $157,850 |
| Work | Maintenance |
| Location | US0080, BRIDGE RAIL REPAIR to IN THE TYLER DISTRICT, Wood County, Tyler District |
| Let / began | 2025-11-12 / 2026-01-02 |
| Latest estimate | 2026-10-01 |
| Contract number | 11251001 |

## Why this score
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.