# Reece Albert, INC.: TxDOT overlay contract 39% complete, US 67, Tom Green County ($22,643,648, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Reece Albert, INC. |
| Subcontractors | K. L. Durham Construction, L.L.C. (2.12%); D. I. J. Construction, INC. (3.26%); Double A Contracting, L.P. (0.4%); Hjc Farms, INC. (1.35%); Scr Civil Construction, LLC (0%); Contractors Service, LTD. (0.6%); J. H. Oden Contracting Company (0.09%); Jb Pinnacle Group, LLC (4.07%); Primate Construction, LP (0.61%); Diibs Specialists, LLC (1.04%) |
| Progress | 39.42% complete, 52.61% of time used |
| Amount | $22,643,648 revised (original $20,466,166) |
| Change orders | $1,627,447 |
| Paid to date | $8,709,156 |
| Work | Overlay |
| Location | US 67, SL 306 to CHADBOURNE ST., Tom Green County, San Angelo District |
| Let / began | 2025-09-04 / 2025-11-03 |
| Latest estimate | 2026-10-06 |
| Contract number | 9253003 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.