# Relmco, INC.: TxDOT bridge replacement contract 61% complete, IH 35, Medina County ($12,823,667, 9 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | Toro Bravo Construction, LLC (0.08%); Texas Shafts, INC. (5.86%); Diibs Specialists, LLC (0.42%); Texas Materials Group, INC. (28.11%); Houston Sawing & Drilling (0.09%); Pinnacle Grinding And Grooving LLC (0.09%); Trp Construction Group, LLC (0.85%); D&G Energy Corporation (1.84%); Hermanos Steel, LLC (0%) |
| Progress | 61.43% complete, 90.57% of time used |
| Amount | $12,823,667 revised (original $12,823,667) |
| Paid to date | $7,877,197 |
| Work | Bridge Replacement |
| Location | IH 35, SH 173 to FM 463, Medina County, San Antonio District |
| Let / began | 2024-11-06 / 2025-06-09 |
| Latest estimate | 2026-10-05 |
| Contract number | 11243010 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.