# Relmco, INC.: TxDOT bridge replacement contract 97% complete, FM 2676, Medina County ($4,283,250, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | Farr Foundation, INC. (7.28%); Aaa Drilling Foundation Company, INC. (5.39%); Toro Bravo Construction, LLC (1.26%); Diibs Specialists, LLC (1.51%); Wims Environmental Construction, LTD. (1.13%); Gregory Pile Driving, INC. (7.22%); Flasher Equipment Company (0.51%); Texas Materials Group, INC. (4.54%) |
| Progress | 97.44% complete, 100% of time used |
| Amount | $4,283,250 revised (original $4,254,250) |
| Change orders | $29,000 |
| Paid to date | $4,173,500 |
| Work | Bridge Replacement |
| Location | FM 2676, 1.52 MI E. OF SH 173 to AT HONDO CREEK, Medina County, San Antonio District |
| Let / began | 2022-12-02 / 2022-12-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 12223232 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.