# Relmco, INC.: TxDOT maintenance contract 59% complete, CR, Presidio County ($28,642,840, 3 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | Ralph A/C Limited Liability Company (4.45%); D&G Energy Corporation (7.11%); Lefever Building Systems, INC. (0%) |
| Progress | 58.8% complete, 136.9% of time used |
| Amount | $28,642,840 revised (original $27,750,000) |
| Change orders | $337,840 |
| Paid to date | $16,516,850 |
| Work | Maintenance |
| Location | CR, TEXAS / MEXICO BORDER ON RAIL LINE to INTERSECTION OF CR 31 / RAIL LINE, Presidio County, El Paso District |
| Let / began | 2024-03-05 / 2024-08-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 3243039 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.