# Relmco, INC.: TxDOT bridge replacement contract 91% complete, SL 368, Bexar County ($7,228,734, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | Toro Bravo Construction, LLC (0.62%); Flasher Equipment Company (0.52%); Light It Up Electric (3.37%); Texas Icon Construction, LLC (0.95%); Texas Materials Group, INC. (3.99%); Hb Farmer Foundation, LLC (6.35%); S & S Bridge Painting, INC. (0.16%) |
| Progress | 90.9% complete, 118.3% of time used |
| Amount | $7,228,734 revised (original $6,974,797) |
| Change orders | $253,937 |
| Paid to date | $6,570,850 |
| Work | Bridge Replacement |
| Location | SL 368, AT SALADO CREEK AND IRA LEE RD. to ., Bexar County, San Antonio District |
| Let / began | 2021-04-07 / 2021-07-12 |
| Latest estimate | 2026-10-06 |
| Contract number | 4213003 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.