# Relmco, INC.: TxDOT bridge replacement contract 88% complete, UA 281, Atascosa County ($4,907,233, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | Murray Construction (0.61%); Toro Bravo Construction, LLC (1.16%); Flasher Equipment Company (0.73%); Gregory Pile Driving, INC. (5.04%) |
| Progress | 88.4% complete, 100% of time used |
| Amount | $4,907,233 revised (original $4,880,363) |
| Change orders | $26,870 |
| Paid to date | $4,338,207 |
| Work | Bridge Replacement |
| Location | UA 281, AT ATASCOSA RIVER to ., Atascosa County, San Antonio District |
| Let / began | 2024-05-03 / 2025-01-21 |
| Latest estimate | 2026-10-05 |
| Contract number | 5243215 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.