# Relmco, INC.: TxDOT newlocation non-freeway contract 100%+ complete, CR, Williamson County ($2,589,521, 9 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | Houston Sawing & Drilling (0.24%); Gk Construction, LLC (0.14%); Diibs Specialists, LLC (0.89%); D. I. J. Construction, INC. (0.83%); Murray Construction (0.44%); Wims Environmental Construction, LTD. (5.13%); Wylie Drilling & Drainage, INC. (1.97%); Texas Materials Group, INC. (5.87%); Pinnacle Grinding And Grooving LLC (0.24%) |
| Progress | 100.13% complete, 111.89% of time used |
| Amount | $2,589,521 revised (original $2,578,219) |
| Paid to date | $2,581,545 |
| Work | Newlocation Non-Freeway |
| Location | CR, CR 119 to 0.45 MILES EAST OF CR 119, Williamson County, Austin District |
| Let / began | 2023-06-27 / 2024-03-04 |
| Latest estimate | 2026-10-05 |
| Contract number | 6233434 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.