# Relmco, INC.: TxDOT traffic protection devices contract 89% complete, US 83, Dimmit County ($3,112,898, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | D&G Energy Corporation (15.15%); R&T Construction (0%) |
| Progress | 88.7% complete, 124.81% of time used |
| Amount | $3,112,898 revised (original $2,887,281) |
| Change orders | $225,617 |
| Paid to date | $2,761,072 |
| Work | Traffic Protection Devices |
| Location | US 83, LOOP 517 to 0.87 MI SOUTH OF LOOP 517, Dimmit County, Laredo District |
| Let / began | 2023-06-27 / 2024-03-25 |
| Latest estimate | 2026-10-02 |
| Contract number | 6233455 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.