# Relmco, INC.: TxDOT bridge replacement contract 39% complete, CR, Live Oak County ($4,876,307, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | A K Fuquay Construction (2.21%); Diibs Specialists, LLC (2.04%); Ancortex, INC. (9%); Highway Barricades And Services, LLC (0.52%) |
| Progress | 38.98% complete, 32.14% of time used |
| Amount | $4,876,307 revised (original $4,876,307) |
| Paid to date | $1,901,027 |
| Work | Bridge Replacement |
| Location | CR, STR. (AA0156001) SALT CREEK to APPROX. .70 MI E OF SH 72, Live Oak County, Corpus Christi District |
| Let / began | 2025-06-04 / 2026-02-02 |
| Latest estimate | 2026-10-02 |
| Contract number | 6253014 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.