# Relmco, INC.: TxDOT bridge replacement contract 75% complete, US 190, Crockett County ($5,673,708, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Relmco, INC. |
| Subcontractors | Diibs Specialists, LLC (1.43%); Bag Reinforcing LLC (0.96%); Texas Environmental Management - San Antonio, INC. (0.91%); Kingz Industrial LLC (2.67%) |
| Progress | 74.64% complete, 113.09% of time used |
| Amount | $5,673,708 revised (original $5,673,708) |
| Paid to date | $4,234,776 |
| Work | Bridge Replacement |
| Location | US 190, AT LIVE OAK DRAW to ., Crockett County, San Angelo District |
| Let / began | 2024-09-05 / 2025-04-08 |
| Latest estimate | 2026-10-06 |
| Contract number | 9243029 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.