# Reynolds & Kay, LTD.: TxDOT maintenance contract 44% complete, US0069, Smith County ($4,944,546, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Reynolds & Kay, LTD. |
| Subcontractors | West Texas Rock Resources, LLC (0.4%); Brydl Contracting, LLC (11.04%); Striping Technology, L.P. (99.97%) |
| Progress | 44.42% complete, 100% of time used |
| Amount | $4,944,546 revised (original $4,944,538) |
| Paid to date | $2,196,340 |
| Work | Maintenance |
| Location | US0069, VARIOUS ROADWAYS IN to SMITH & CHEROKEE COUNTIES, Smith County, Tyler District |
| Let / began | 2023-11-01 / 2024-02-05 |
| Latest estimate | 2026-10-01 |
| Contract number | 11234030 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.