# Reynolds & Kay, LTD.: TxDOT maintenance contract 24% complete, US0259, Gregg County ($10,318,775, 3 subs)

**Score:** 85/100

| Field | Value |
|---|---|
| Prime contractor | Reynolds & Kay, LTD. |
| Subcontractors | Striping Technology, L.P. (38.96%); Brydl Contracting, LLC (6.1%); West Texas Rock Resources, LLC (0.25%) |
| Progress | 23.9% complete, 87.49% of time used |
| Amount | $10,318,775 revised (original $5,035,051) |
| Change orders | $5,283,724 |
| Paid to date | $2,466,253 |
| Work | Maintenance |
| Location | US0259, VARIOUS ROADWAYS IN to GREGG & RUSK COUNTIES, Gregg County, Tyler District |
| Let / began | 2023-11-02 / 2024-02-14 |
| Latest estimate | 2026-10-01 |
| Contract number | 11234221 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.