# Reynolds & Kay, LTD.: TxDOT hazard elimination & safety contract 82% complete, CS, Smith County ($552,228, 4 subs)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Reynolds & Kay, LTD. |
| Subcontractors | Striping Technology, L.P. (53.21%); Southwest Environment Services LLC (1.69%); Cap River LLC (0.51%); Flex Supply, LLC (1.17%) |
| Progress | 82.07% complete, 62.2% of time used |
| Amount | $552,228 revised (original $539,227) |
| Paid to date | $442,536 |
| Work | Hazard Elimination & Safety |
| Location | CS, AT ROSE RUDMAN TRAIL to AND HUBBARD MIDDLE SCHOOL, Smith County, Tyler District |
| Let / began | 2026-01-07 / 2026-04-09 |
| Latest estimate | 2026-10-02 |
| Contract number | 1263226 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.